5S SF
Last updated
Last updated
In the section SIM SF Questions Configuration - by Line:
Select 5s checklist.
Select Production Area, Line/cell Group, Date, Shift.
DLMO creates the list of question defined in configuration, for the line in a Shop Floor checklist (example in figure), or for the department in in an Office Checklist:
Pictures are shown according to the question sorting them. If more than one picture is associated with the same question, pictures are shown in alphabetical order.
For each question, it is possible to insert the result of the check (“OK” or “Not OK”), create an action, add a picture and add a comment.
Not compiled result is considered, in the results evaluation, as “Not OK”.
The selected results are highlighted in green (OK) and in red (Not OK)
SHOP FLOOR 5S RESULTS: Results are aggregated by shift for SIM1, by Production Area for SIM2 and by Plant for SIM3 -SIM5, with the following rules:
Result: is calculated as Number OK results / Number of questions (in %). Blank (not filled) checks are considered as not OK results.
Cell background color:
Gray: no checklist executed
Red : from 0% to 69%
Yellow : from 70% to 89%
Green : from 90% to 100%
*: means that there are checklists not started for at least one shift, regardless of the results.
First clicking on the date, DLMO shows the result (in %). With a second click on the date, DLMO opens the detailed page of the “not OK”results.
Switch “View all answers” to on to view all answers for the selected day.
Checklist is started pressing the button .
In Result section it is possible to view the results of all the 5S checklists compiled in the last week, for the SIMSF, by all the users of the department.
Clicking on the icon , it is possible to view actions, pictures and comments added in the execution.